The construction progress of Sorgun Wastewater Treatment Plant Project as of the end of December 2021 is as follows:
1- The construction progress of guardhouse has been completed. (Reinforced Concrete) – Structure No.30
2- The construction progress of workshop building is at 65% level. (Reinforced Concrete) – Structure No.29
3- The construction progress of administrative building is at 55% level. (Reinforced Concrete) – Structure No.28
4- The construction progress of distribution structure aeration tanks is at the level of 98%. (Reinforced Concrete) – Structure No.10-11
5- The construction progress of recirculation station is at the level of 45% – Structure No.16
6- The construction progress of Bio-P-Tank is at 95% level. – Structure No.8-9
7- The construction progress of drainage pump station is at the level of 45%. – Structure No.25
8- The construction progress of pre-treatment units is at the level of 75%. – Structure No.1-2-3-4-5-6
9- The construction progress of service water disinfection unit is at 55% level. – Structure No.30
10- The construction progress of final sedimentation tanks is at 95% level – Structure No.14a-14b
Within the scope of Sorgun Waste Water Treatment Plant Project, the reinforced concrete works of the process units continued in September 2021.